Why we lock selections before we break ground

A tile chosen in month six costs more than the same tile chosen in month one, and not because the tile got more expensive.

By [Name], Director

Materials and finishes samples laid out

Every selection carries a decision behind it that someone has to make earlier. Tile size affects the screed. Tapware affects rough-in. A freestanding bath affects the slab penetration. Deciding late does not delay the decision, it delays the trade.

The cost of a late change

Changing a bathroom layout after rough-in means a plumber returns, a wall is opened, waterproofing is redone and the tiler is rescheduled. The product might be a two hundred dollar difference. The change is four thousand.

Selections are not decoration. They are construction information.

How we run it

Selections happen during the design stage, over several appointments, with a schedule that gets signed off and attached to the contract. Nothing on that schedule is a placeholder. Where a client genuinely cannot decide, we choose a real product and price it rather than carry an allowance.

It is more work up front, and it is the single biggest reason our builds finish close to their contract price.

Keep reading

All entries
Cost

What a block costs you before you build on it

6 min read

Contracts

Fixed price contracts, and what "fixed" actually means

5 min read

Planning

Knock-down rebuild or renovate: how we help clients decide

7 min read